FEBRUARY 2024- NOTIFICATION OF SITE ACTIVITIES
Agnico Eagle Mines is pleased to provide an update on current activities at and surrounding the Upper Beaver Project site.
As a follow-up to our notification of site activities distributed in January 2024, Agnico Eagle would like to provide an update related to the work along Beaverhouse Road. This work is in preparation for the potential start up of the Advanced Exploration Project anticipated later this year, pending internal approval.
Vehicle pullovers are now complete at various locations along Beaverhouse Road. Vegetation brushing and tree cutting is ongoing. Mobilization of logging equipment to site is also anticipated by March 1st. Please note that all heavy equipment will be using Agnico Eagle’s private McBean Road entrance off Highway 66 to access the Beaverhouse Road and Upper Beaver site.
As part of Agnico Eagle’s commitment to safety, various measures have been initiated. An internal traffic control plan for brushing and logging is in place to ensure the safety of all road users and includes, but is not limited to, radio communication plan, clear signage and additional signage in active work areas, speed reduction, and mitigation measures. While we strive to maintain clear roadways, please note that some debris may be present in areas undergoing work. Rest assured that our dedicated crew is diligently working to swiftly remove any debris to minimize inconvenience while ensuring road safety.
The map below highlights the main access that will be used, as well as the vehicle pullover locations:
In addition, there is currently a drill at site, near the proposed exploration shaft location, undertaking a grouting program. This program is ongoing and aims to seal the bedrock around the future exploration shaft to avoid water infiltration.
As a follow up to our October 2023 notice, Agnico Eagle began to pump storm water accumulated in the exploration shaft collar area with limited success. After consideration, and to improve effectiveness, the pumping will be augmented using Story Environmental’s approved mobile system.
Agnico Eagle values transparency and community engagement and is committed to keeping you informed about our activities. If you have any questions, concerns or would like to request further information or make suggestions to improve our practices, please do not hesitate to reach out to Amy Danchuk, our Community Relations Coordinator, at 705-567-4377 ext 4131242 or relations.upperbeaver@agnicoeagle.com.
Any questions or concerns about the Upper Beaver Project or Agnico Eagle’s activities? Feel free to reach out to our team. We look forward to talking with you!
Email: relations.upperbeaver@agnicoeagle.com
Website: www.upperbeaver.agnicoeagle.com
Community Relations Tel: 705.567.4377 ext 4131242
Exploration Office: 72 Upper Canada Drive ON.
P0K 1B0